Tuesday, July 16, 2013

We finally have a Slab

Site start was suppose to be 28th of June and slab 9th July, but work didn't commence till 29th when we spoke to the SS the following Thursday we were told there might be a delay in pouring the slab due to back log. a definite delay if the weather wasn't good. We decided to go with an independent inspector as lot of people on homeone forum had recommended. We had to keep them informed about the slab as well. So we asked our SS to keep us informed of any delays.

Monday  8th of July our SS let us know that the  slab will be poured on Wednesday instead of Tuesday. More waiting...

They did pour the slab on Wednesday. Independent inspection was booked for Friday.