Saturday, August 31, 2013


week 9 August 23 -30
It was quite an eventful week. With some very shocking news.


Saturday drove past the site was still able to go in as the front door was open. Insulation done.

by Wednesday plasterboard done.




cant believe how quick things are going and our SS has been great and top of things. He told us he concentrates more on the quality of the build than how quick. we are very happy with the pace things are progressing and how its looking so far.

brick work almost complete, we are pretty sure will receive the lock up invoice soon. Even though we are still missing our bi-fold. as it seems to be the trend.




                                                           timber infill

Friday morning we received a call from our SS saying brick work would complete beginning of next week. and that he has been transferred to a different estate other side of Melbourne :( :( our new SS will be taking over.

why why oh y ????????????????????

Guess things were going too smoothly. all good things must come to an end.

We were finally feeling positive about the PD building process. after the drama etc through the admin process.



And the problems begin........

drove past on Friday noticed the windows aren't in the same height someone s made a mistake and now there s a big white piece of timber infill. on one. not very happy with this. contacted  Our new SS informed him about it and wanted to attend it before the brickies finish work. Not a good start he was saying everything's according to plan.

finally manage to agree to meet us on site on Monday.